St. John Compressor Station Project
A proposed natural Gas project
TC Energy is one of North America’s leading energy infrastructure companies with operations in natural gas and power industries.
The ANR Pipeline Company (ANR), a subsidiary of TC Energy, is preparing to replace natural gas compressor facilities at its St. John Compressor Station located in Lake County, Indiana, to increase the reliability, safety, and long-term integrity of the compressor station and ANR’s system.
Specifically, the proposed Project includes replacing seven existing obsolete compressor units with two Solar Turbines Taurus-70 units and one Solar Turbines Mars-100 unit.
The modern turbine compressors, which operate smoother with less vibration, will reduce emissions and noise levels at the station once complete.
The system will also operate more efficiently to meet ongoing demand for natural gas to provide power and heating to homes, while lowering emissions.
Pre-construction activity is targeted to begin in June 2024, with an estimated completion date of December 2025.
Fact & Figures
Modern turbine compressors will reduce greenhouse gas emissions
Lower vibration will reduce operating noise
Increased reliability and safety of St. John Compressor Station
Estimated project timeline
Construction preparation
June 2024
Construction begins
August 2024
In-service
September 2025
Completion
December 2025
Dates shown are based on current understanding of the facts and are subject to change.
CONSTRUCTION
All Project construction activities, including the installation of the new compressor units, will be confined to our existing property.
The anticipated Project construction hours will typically be: Monday to Friday - 7 a.m. to 5 p.m., Saturday - 8 a.m. to 5 p.m. and Sunday - 9 a.m. to 5 p.m.
Select portions of the Project may extend beyond construction hours due to the nature of work; should this occur, the community will be informed in advance.
The first working hour will be utilized for daily preparations and should have minimal noise impacts.
Mitigative noise measures, including an additional wall barrier and white noise back-up alarms, will also be put in place.
Stay informed as we post our latest Construction Updates, below.
October 3, 2024
Update: The Project will mobilize oversize loads starting the week of October 7 through October 31. This will entail the use of police escorts and periodic road closures on White Oak Avenue for short durations.
On Wednesday, October 9, the Project must start work at 6 a.m. This is required to complete the type of work scheduled for this day. The Project will make every effort to minimize any potential impacts of noise and lighting.
Starting October 14 through October 28, the Project will have additional work outside of our standard construction hours. Due to the extended hours, there may be noise and visible lighting in the evening. This is necessary due to the welding process that is required for this phase of the Project. We do not anticipate evening work to exceed 8 p.m.
This phase also entails an outage of our facility. To minimize impacts to our customers, including NIPSCO, the Project must work for longer durations. Once this two-week phase is complete, the Project will return to its standard construction hours.
Impacted road: We anticipate that this activity will impact primarily the roads of West 93rd Avenue and White Oak Avenue.
Road closure: We do anticipate periodic closures on White Oak Avenue for short durations. We will abide by the required hours issued in our hauling permits.
August 26, 2024
Update: The Project has completed its pre-construction preparation activities. Starting the week of August 26, the Project will begin foundational work at the site including excavating and the installation of helical piles. These types of activities will require multiple trucks to enter and exit the area during our project work hours over the next three weeks.
Impacted road: We anticipate that activity will impact primarily the roads of West 93rd Avenue and White Oak Avenue.
Road closure: We do not currently anticipate any road closures but will utilize flaggers as needed.
August 13, 2024
Update: During the week of August 12, the Project will begin a full mobilization of equipment to our site. This will include the transportation of office trailers and heavy equipment. Most of the traffic flow will last approximately two weeks.
Impacted road: We anticipate that activity will impact primarily the roads of West 93rd Avenue and White Oak Avenue.
Road closure: We do not currently anticipate any road closures but will utilize flaggers as needed.
August 5, 2024
Update: During the week of August 5, preliminary construction preparation will continue at our Project site. This will include the continuation of slit trenching and hydrovacing. These activities are required to safely excavate around utilities and will produce noise during the work hours of our Project.
The Project also anticipates beginning the mobilization of office trailers.
Impacted road: We anticipate that activity will impact primarily the roads of West 93rd Avenue and White Oak Avenue.
Road closure: We do not currently anticipate any road closures but will utilize flaggers as needed.
July 15, 2024
Update: Preliminary construction preparation will continue at our Project site. During the week of July 22, we anticipate the start of slit trenching and hydrovacing. These activities are required to safely excavate around utilities and will produce noise during the work hours of our Project.
Impacted road: We anticipate activity will impact White Oak Avenue as select heavy equipment mobilizes to our Project site in addition to the commute of our contractors.
Road closure: We do not currently anticipate any road closures.
June 24, 2024
Update: Construction activity will begin on June 24 with dump trucks moving materials to and from the Project site.
Impacted road: We anticipate activity will impact White Oak Avenue.
Road closure: We do not currently anticipate any road closures.
Community benefits
Our projects offer long-term economic benefits and help strengthen local, state and national economies in three key areas.
Employment and business opportunities — As we move into the construction phase of any project, we require equipment operators, welders, mechanics, truck drivers, laborers and more. We also have a demand for local goods and services. Learn more about working with us at our Contractors, Suppliers and Vendors portal.
Annual revenue to support local services — Project construction results in tax payments to all levels of government. When the Project is operational, annual tax payments help support schools, hospitals, emergency services and other local programs vital to communities.
Supporting local communities — We have a rich history of giving back to local and Indigenous communities where we live and work. Our Build Strong community investment program builds strong and vibrant communities by providing grants and donations that support community groups and initiatives, as well as awarding scholarships to our future energy problem solvers. Visit TCEnergy.com/BuildStrong to learn more about our social impact program and how to apply for funding.
Introducing TC Energy
We encourage you to learn more about who we are and our approach to sustainability.
Frequently asked questions
Who is TC Energy and what do you do?
We’re a team of 7,000+ energy problem solvers working to move, generate and store the energy North America relies on. Today, we are taking action to make that energy more sustainable and more secure. We are innovating and modernizing to reduce emissions from our business, and we are delivering new energy solutions – from natural gas and renewables to carbon capture and hydrogen – to help other businesses and industries decarbonize too. TC Energy is an energy infrastructure company that for more than 70 years – and in this area, over 100 years – operated pipelines, storage facilities and power-generation plants that support life in the U.S., Canada and Mexico safely, reliably and quietly.
Are the Solar Turbines compressor station units solar powered?
No. Solar Turbines is the manufacturer of the compressor unit turbines, but they are not solar powered.
Why are you replacing the existing compressor station units?
By replacing the seven existing reciprocating compressor units with three modern Solar Turbines units, we can improve operational sustainability, decrease vibration, reduce greenhouse gas emissions and operational sound levels, while gaining maintenance and operational efficiencies and improving the reliability, safety and long-term integrity of the St. John Compressor Station and ANR’s Pipeline System.
How are you reducing greenhouse gas (GHG) emissions?
Replacement and modernization of older compressor units with more efficient units and modern technology will result in decreased emissions.
Are your compressor stations safe?
TC Energy’s ANR Pipeline System and related metering and compressor stations have operated safely for the more than 70 years. Safe and efficient natural gas delivery is a foundational value for TC Energy and its employees. Through more than a century of operating experience and technological advancement, we have developed one of the safest and most reliable energy transportation networks in the world. We monitor our system 24 hours per day, seven days per week, and are constantly utilizing the latest in technology to maintain the highest possible integrity standards.
How will you limit your environmental impact during construction?
New compressor station units and construction activities will be located on the existing St. John Compressor Station site. Construction will use a temporary workspace.
Ways to reach us
We’re here to answer your questions. For general questions you can contact us by email, but for a quicker response, please call us directly.
U.S. Projects Landowner Hotline
Write to us
700 Louisiana Steet
Houston, Texas 77002